admin
Northeast Power Coordinating Council - Cross Border Regional Entity Home Robert Moses Hydro Electric Dam courtesy of New York Power Authority Raddison Substation courtesy of TransEnergie HydroQuebec NY Skyline courtesy of ConEd

NPCC Inc. Procedures, designated as Type "C" documents and identified as NPCC Inc. Document C-nn, provide for uniform implementation, interpretation and monitoring of conformance with the general criteria, guides and reporting requirements of the Type "A" and "B" documents. Type "C" documents are prepared and revised by one of the five NPCC Inc. Task Forces which is responsible for the discipline addressed in the given procedure.

Start Date:         End Date:        

Procedures

DocumentPosted
C-37 Operating Procedures for Ace Diversity Interchange 08/14/2008
C-42 Procedure for Reporting and Reviewing System Disturbances 08/14/2008
C-43 Operational Review for the Integration of New Facilities 08/14/2008
C-25 Data Contacts List 07/25/2008
C-17 Appendix A--Reporting Form 11/08/2007
C-17 Procedures for Monitoring and Reporting Critical Operating Tool Failures 11/08/2007
C-25 Procedure to Collect Power System Event Data 09/25/2007
C-44 NPCC, Inc. Regional Methodology and Procedures for Forecasting TTC and ATC 09/25/2007
C-29 Procedures for System Modeling:Data Requirements and Facility Ratings 05/08/2007
C-38 Procedure for Operating Reserve Assistance 04/26/2007
C-40 Procedures for Inter-AREA Voltage Control 04/26/2007
C-15 Procedures for Solar Magnetic Disturbances Which Affect Electric Power Systems 01/11/2007
C-35 NPCC Inter-Area Power System Restoration Procedure 01/11/2007
C-39 Forms C-39 Forms and Instructions 11/30/2006
C-39 Procedure to Collect Major Disturbance Sequence Data 11/30/2006
C-00 Listing of NPCC Documents by Type 08/10/2006
C-33 Procedure for Analysis and Classification of Dynamic Control Systems 04/06/2006
C-13 Operational Planning Coordination 03/01/2006
C-03 C-03 Replaced by C-36 08/18/2005
C-36 Procedures for Communications During Emergencies 08/18/2005
C-16 Procedure for NPCC Review of New or Modified Bulk Power System Special Protection Systems (SPS) 08/10/2005
C-22 Procedure for Reporting and Reviewing Proposed Protection Systems for the Bulk Power System 06/28/2005
C-22 Form Form for C-22 06/28/2005
C-30 Procedure for Task Force on System Protection Review of Disturbances and Protection Misoperations 06/28/2005
C-20 Procedures During Abnormal Operating Conditions 05/19/2005
12